Menu
Log in
Home Page

Timeline

School governors and other senior leaders took part in a Pre-Start meeting with the HCC Team and Apex Contractors Ltd (the development contractors) on 9th September 2022.

 

Weekly meetings will be taking place throughout the academic year to ensure that that the project runs as smoothly as possible.

 

The building works commenced on 26th October 2022 and it is anticipated that the school will be in a position to welcome 60 Reception pupils as from September 2023.

 

Progress Update – December 2022

  • Reduced level dig completed and piling mat installed.
  • Excavation completed for attenuation tank.
  • Foul and surface water drainage installed to the rear of the building.

 

 

Upcoming Works – January 2023

  • Install pile foundations.
  • Excavate and form reinforced concrete ground beams.
  • Install attenuation tank and surface water drainage to the front of the building.
Top